A printout of the walkthrough for the new ICTAS Facility is now available. Download here.
|
|
ICTAS II
- 42,000 square feet in Life Sciences Corridor of the VT campus
- $35,000,000 total budget, $23,000,000 construction budget
- Skanska selected to be Construction Manager at Risk
- Construction began in April 2009.
- Projected occupancy is January 2011.
- Targeted technology areas include Nanobiotechnology, Nanosensors, Bioengineering and Biomaterials, and Water.
|
|
|